Orchard Mesa Pool Ballot Issue 2B: Costs and Repair Plans

On Tuesday, November 3, Grand Junction voters decide City Ballot Issue 2B. It would raise the city sales and use tax by seven hundredths of a percent to repair the Orchard Mesa Pool. The pool sits at 2736 Unaweep Avenue. Its condition has been known since 2023, when a study found its systems at the end of their useful life. What changed this fall is the city around it. The Community Recreation Center at Matchett Park opened on September 25, 2026. With a new indoor pool now open north of the river, 2B asks whether Grand Junction will pay to keep a second one on the Orchard Mesa side.

What September 25 Changed

The CRC was always part of this decision. At a February 2, 2026 council workshop, staff laid out four options for the Orchard Mesa Pool. One was to keep operating it after the CRC opened. Another was to close it when the CRC opened. A third was to seek a public-private partner through a request for proposals. The fourth was to ask voters about forming a Title 32 special district in the Orchard Mesa portion of the city that would take over the pool. Council first chose the partnership route and asked for more information on the special district. By August, it had settled on a citywide ballot question.

Staff numbers from that February workshop show why the CRC opening matters. Once the new center opened, the city projected each visit to the Orchard Mesa Pool would cost about $30 in public subsidy. Running the pool as it is would take about $400,000 a year and serve about 14,400 visits.

Facility Subsidy per visit, February 2026 staff estimate
Orchard Mesa Pool, after CRC opens About $30
Lincoln Park Pool $8.60
Community Recreation Center $3.12, estimated

A gap of nearly ten to one between the two indoor pools explains why closing the Orchard Mesa Pool was ever on the table. It also shows what 2B is really about. The repair plan keeps the pool the same size, so a yes vote funds the neighborhood pool as a neighborhood pool, with no expansion.

What 2B Pays For, and What It Doesn't

The council resolution that sent the question to voters spells out the limits of the work:

"The work does not include an expansion beyond the current 6 lane, 25 yard by 25 meter, configuration. The work is therefore a repair or a fixing of the pool and not a remodel, which would include an expansion."

The repair would replace the mechanical, HVAC, electrical and filtration systems and other operating hardware. According to the city's Orchard Mesa Recreational Facility project page, the updated estimate also covers refurbishing the locker rooms and replacing the hot tub, which does not work. Here is how the money would work, based on the resolution and Mesa County's 2026 General Election TABOR booklet:

  • Tax rate: The city sales and use tax would go from 3.39% to 3.46% starting January 1, 2027.
  • First-year revenue: About $1.9 million in 2027, the first full fiscal year.
  • Debt: Up to $12 million in principal. The county booklet lists a maximum annual repayment cost of $1.9 million.
  • Step-down: After the debt is paid off, the rate drops by 0.04 percentage points on the next January 1, and no later than December 31, 2047.
  • What stays: The remaining 0.03 points continue as permanent funding for the pool's operation and maintenance.

That last item gets less attention than the repair price. The resolution estimates the yearly cost of operating and maintaining the pool at $700,000, so 2B funds both the repair and the pool's yearly operating gap. February's staff estimate for running the pool as it is came to about $400,000 a year.

Councilmember Cody Kennedy of District A explained the split to KJCT as "basically 7 cents on $100 spend." He said roughly half pays off the rebuild and the rest is an ongoing subsidy, and that the debt portion would end when the debt is paid, "say 15 years."

Why the Dollar Figures Don't Agree

Four price tags have circulated since August, each measuring something different:

  • About $10 million: The construction estimate reported by Western Slope Trellis.
  • $11.6 million: The resolution's estimate for repairing, renovating and equipping the pool. Trellis uses the same number for the debt issued after financing.
  • $12 million: The most debt principal the ballot question allows, and the round number Kennedy used.
  • $19 million: The total repayment cost, principal plus interest, listed in the TABOR booklet.

The city's cost figure comes from a 2023 study by OLC, also called Ohlson Lavoie Corporation. FCI reviewed it in August 2026 to update the total, and FCI's letter is posted on the city's project page. FCI is the same firm that served as construction manager and general contractor for the CRC.

The Deadline Behind the Ballot

The vote is happening now, and not after more study, because of the calendar. Here is how the pool got to November 3:

  1. 1983: The pool opens as a joint project of the City of Grand Junction, Mesa County and Mesa County Valley School District 51. District 51 provides the land and still owns the building. The city runs the pool.
  2. 2023: The OLC study finds the mechanical, pool and building systems at the end of their useful life.
  3. Fourth quarter 2025: The city starts paying the pool's full cost. Under the earlier arrangement, the city and county split the yearly subsidy.
  4. February 2, 2026: Council reviews the four options.
  5. August 3, 2026: Council reviews the 2026 Community Satisfaction Survey. KJCT reported that residents were split on raising taxes or borrowing for the pool, with stronger support for letting voters decide.
  6. August 19, 2026: Council votes unanimously to put the question on the ballot.
  7. September 25, 2026: The CRC opens at Matchett Park.
  8. November 3, 2026: Election day. The county clerk runs the city's question as part of the coordinated election.
  9. End of 2026: The city's operating agreement for the pool expires.

Western Slope Trellis reported that District 51 has signaled plans to demolish the building when the agreement expires unless there is a long-term fix. That is a reported signal, not a final demolition order. Still, it explains why the 2B timeline is short. The resolution says that if voters approve, the city will start the project "as soon as possible."

The Case Supporters Have Made

Supporters have been organized for years. Mariann Taigman of the Save the Orchard Mesa Pool Committee told KJCT in August that it had been "6 long years" since the group formed. She said the city survey showed 66% of the community favored putting the question on the ballot. Her argument is about capacity: "with our ever-growing population, our valley really needs two indoor community swimming pools."

Carol Ward, another committee member, made a geographic argument in KJCT's earlier report. She welcomed the CRC and said that for many Orchard Mesa residents, getting there "is not going to be feasible." She pointed to kids with working parents and transportation problems during summer. Kennedy, for his part, described the $12 million as more than the city has in discretionary funds. That is why, he said, the council sent the question to voters rather than paying for the repair itself.

The county's TABOR booklet summarizes the written comments filed on the measure. Supporters argued that most city Parks and Recreation amenities sit north of the Colorado River and that the pool is one of the few major ones serving the south side. According to the booklet, no comments against 2B were filed by the constitutional deadline.

Still Running in the Meantime

The pool is still in use while the vote is pending. On October 8, the city's calendar listed a snorkeling class at the Orchard Mesa Pool from 6 to 7:30 p.m., at $84 per session. Before you go for lap swim or open swim, check the city's Orchard Mesa Pool hours page. For the CRC's memberships and hours, see the Community Recreation Center site. The full history of the pool question, the 2023 study excerpt and the August cost update are on the city's Engage GJ project page, which Kennedy recommended as the place to start.

This post is general information about a ballot measure. It is not legal, tax or financial advice, so check how any tax change affects you with the right professional.

Living on Orchard Mesa means keeping track of what's changing on Unaweep Avenue, and the choices this neighborhood makes show up in its daily life for years. If you'd like to talk about what's happening in 81503 and what it means for your home, Your 3A Team is glad to sit down with you. Request a free home consultation.